| Project: | Alaska
Seafood Facility Early Steel Package Anchorage, Alaska |
|
| Owner: |
Alaska Seafood International Richard Holden (907) 278-8800 |
|
| Architect: |
RIM Architects Matt Vogel (907) 258-7777 |
|
| Contract Amt.: | $ 2,400,000 | |
| Start: | March 1998 | |
| Completion: | July 1998 | |
| Project Manager: | John Anderson | |
| Superintendent: | Sam Hill | |
Descriptive: RHC furnished 650 tons of structural steel, 600 tons of steel joists, and 165 tons of metal decking for this 214,700 square feet seafood processing facility. RHC purchased, reviewed shop drawings, and delivered listed materials to the jobsite for erection by a subsequent contractor. The steel erector encountered virtually no shop drawing or fabrication related mistakes while installing the materials RHC furnished. We worked to design documents provided by the Owner. |
||