Anchorage
School District
Summer Sauve
(907) 348-5212
Architect:
Architects
Alaska
Marvin Ungerecht
(907) 272-3567
Contract
Amt.:
$13.7
Million
Start:
May
2005
Completion:
July 2006
Project
Manager:
Karen Bagley
Superintendent:
Larry
McPheters
Descriptive:
The Anchorage
School District sets an aggressive schedule for major summertime
remodels at the local schools. This particular construction
project had only 66 days available for completion. The project
consisted of remodeling 25,000 SF of existing school area (NB
Hall) and adding a 14,400 SF 2nd story with a new 3rd-story
penthouse (Building “D”). The scope of work for NB Hall
incorporated asbestos abatement, roofing, new skylights, and a
total interior demolition and reconstruction that encompassed
43,000 SF.
Despite the
tight schedule, changes in work scope during the project,
unknown and hidden conditions that added more work, RHC still
completed the job on time. As a bonus, Building “D” was
delivered 4 months ahead of schedule. RHC is proud to have
exceeded expectations at Service High School.
RHC was
sensitive to the potential disruption to school operations and
made every effort to meet the schedule in the face of the
challenges. The Alaska chapter of Associated General Contractors
presented RHC the Excellence in Construction Award for this
project – “2007 Challenge of a Job, Between $5,000,000 and
$15,000,000 Vertical Construction.”